Microsoft Project 2010, Managing Projects 認定 070-178 試験問題:
1. You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?
A) Set the Constraint date field.
B) Select the Mark task as milestone check box.
C) Set the Deadline date field.
D) Select the Display on Timeline check box.
E) Set the Finish date field.
2. Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A) Change the maximum units for the resource.
B) Change the working time for the resource.
C) Update the base project calendar.
D) Assign the resource only to tasks that are scheduled on the working days.
3. You attempt to print the task table and Gantt chart horizontally. However, the task names do not appear on each printed page. You need to ensure that the task names are printed on each page.
What should you do?
A) Select the Task Name column and click Add to Timeline.
B) Modify the settings in the Page Setup dialog box.
C) Modify the settings in the Column Settings dialog box of the Task Name column.
D) Modify the settings in the Field Settings dialog box of the Task Name column.
E) Select the Task Name column and click Print.
4. You need to create a project plan that accommodates the corporate holiday calendar. What should you do?
A) Create an interim plan that includes the defined holidays to track the holidays.
B) Add exceptions to the project calendar for corporate holidays.
C) Create a task for each holiday and assign each resource to each holiday task.
D) Adjust the maximum units for each resource to reflect the total working days for the year.
5. You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
A) Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on each project.
B) Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view to manually modify resource Work.
C) Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
D) Open a blank project and select Insert Subproject for each project schedule. Then, use the Level Resource function for selected resources.
質問と回答:
| 質問 # 1 正解: C | 質問 # 2 正解: B | 質問 # 3 正解: B | 質問 # 4 正解: B | 質問 # 5 正解: D |














1343 お客様のコメント
品質保証JPexamはIT認定試験のシラバスに従って、試験問題の範囲を正確に絞って、的中率が99%の最新問題集を捧げます。
1年間の無料更新サービスJPexamは1年以内に問題集の無料更新サービスを提供し、お客様がいつでも最新版の問題集を持つことを保証いたします。もし試験の内容が変更されたら、弊社は直ちにお客様にお知らせします。それに、弊社の問題集が更新されたら、早速メールで最新バージョンを送付いたします。
全額返金JPexamの問題集を利用すると、短時間で勉強しても試験に合格できるのを保証いたします。試験に不合格になってしまった場合、弊社は全額返金いたします。(
ご購入前のお試しJPexamは問題集のサンプルを無料で提供いたします。ご購入前にサンプルを試用して製品の品質を確認することができます。ご遠慮なく利用してください。